Teaching pool, hot tub and changing rooms demolished; main pool remained at the 28 October update.
Phase 1 final inspection planned for November 2026; exact date and completion not yet confirmed.

In Vingåker Municipality’s latest verified status update from 28 October 2026, demolition work at Vingåkersbadet, Storgatan 35, was nearing completion. By that point, the teaching pool, hot tub and changing rooms had already been demolished.

The large main pool was the final remaining part of the demolition at the time of the update. The municipality also stated that a final inspection for phase 1 of the renovation project was scheduled for November 2026.

When checking the municipal primary source on 17 November 2026, no exact date had been specified for the final inspection and its completion had not yet been confirmed.